Projects 603 & 617A Collection System Repairs Construction Update

1

Stark County - OH | Stark County - OH

Stark County - OH | Stark County - OH

S.E.T. Inc. was recently awarded this $3,063,000 project in various areas throughout Perry, Jackson and Plain Townships. Areas of work are: 

Muirfield Ave NW, Carnoustie Circle NW, Avondale St. NW, Freedom Ave N & S, Chippendale to 12th St. Easement, List to Clearbrook Easement, Chippendale St NW, Chadwick to Clearbrook Easement, Clearbrook Rd. NW, and Chippendale to Clearbrook Easement

A Notice to Proceed was issued on February 27th and a pre-construction meeting held on March 2nd. 

The project completion date is October 10, 2023. 

Project 617A:

Insight Pipe Contracting was awarded this $848,358.50 contract in various areas throughout Jackson, Plain and Lake Townships. A general summary of the work is:

  • 8”/10” CIPP and manhole rehab along South Boulevard NW from Fulton Drive NW to Skycrest Drive NW in Jackson Township. 
  • 8” CIPP and manhole rehab along Diamond Street NE between Sapphire Avenue NE and Emerald Avenue NE in Plain Township. 
  • Manhole rehab in an easement along the creek southwest of the Mogadore Avenue NW and Pontius Street NW intersection in Lake Township.
A pre-construction meeting was recently held and work is nearing commencement. The contract completion date is October 12, 2023.

Please contact Wayne Carkido of the Stark County Sanitary Engineers Office for more Information at 330-451-2303.

Original source can be found here

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS